Bids were opened yesterday for the TXDOT improvements along FM 973, constructing a continuous left turn lane and revised shoulders from Blake Manor heading south to just past
TXDOT will officially award the project to Aaron Concrete at the end of the month. Then TXDOT and Aaron Concrete will meet for the preconstruction meeting about 6 weeks later and the Notice to Proceed can be issued right thereafter. In just about 2 months you can expect to see dirt turning and roadway improvements moving forward.
Dwyer Realty Companies, through its partnership entity WildHorse Creekside Development Corporation, is funding the full construction costs of the referenced FM 973 turn lane and shoulder improvements on behalf of the City of